How to manage an evaluation conducted by an external consultant?

Many Emerging Development Partners (EDPs) engage external consultants to conduct an independent evaluation of a development cooperation intervention. However, commissioning an external evaluation does not mean fully handing over responsibility for the evaluation to the consultant. The commissioning office remains responsible for ensuring that the evaluation is relevant, credible, useful, and conducted to an appropriate standard of quality.

What this helps you do

This guide provides a practical, step-by-step approach to managing an evaluation conducted by an external consultant.

When to use it

When managing an evaluation to be conducted by an external consultant.

1Decide and prepare

Before commissioning an evaluation, organize a meeting with those involved in implementing the intervention to clarify the following key questions and help define the Terms of Reference (ToR) of the evaluation:

  • Why is the evaluation being conducted?
  • What decision, learning or accountability need will it serve?
  • Who are the intended users of the evaluation results?
  • What intervention, period and results will be assessed?
  • What resources and time are available to support the evaluation?

2Prepare a clear Terms of reference (ToR)

The ToR establishes the foundation for the evaluation. It should provide sufficient direction and clarity while allowing the evaluator to exercise professional judgement and reach independent conclusions. A well-designed ToR should clearly specify the purpose of the evaluation; provide a description of the intervention, including its intended results; define the evaluation objectives and scope; set out the evaluation questions and methodological requirements; and specify the expected deliverables and timetable.

TemplateSample evaluation ToR from ESCAPDownload coming soon

3Select the evaluator

The evaluator may be an experienced evaluator from the evaluation office of the EDP or implementing organization. However, many EDPs also rely on external consultants to conduct evaluations. When selecting an external evaluator, it is important to identify a candidate with substantial experience in conducting evaluations and who can provide relevant samples of evaluation reports he/she has authored. A common mistake is to engage a subject-matter expert based primarily on their technical expertise without sufficiently demonstrated experience in evaluation.

Assess candidates against:

  • Relevant evaluation experience
  • Experience in the development cooperation context
  • Understanding of the subject matter to be evaluated
  • Good communication and writing skills (Conduct an interview and review sample evaluation reports)
  • Understanding of cultural and institutional contexts
  • Independence and absence of conflicts of interest (Don’t engage a consultant who has been involved in the design and implementation of the intervention)
  • Availability within the required timeframe and available budget

Key principle

Do not select an evaluator solely because they are subject-matter expertise.

4Manage the inception phase

Once the consultant is selected and recruited, organize an inception meeting inviting the relevant key members of the implementing team and the consultant. The meeting should clarify the evaluation purpose, scope and process. Most importantly, there should be a discussion on how the eventual evaluation results will be used by the commissioning agency. Following the inception meeting, the commissioning agency may also organize separate interviews between the consultant and the members of the intervention team to clarify further the design and implementation of the intervention and their insights on how to make the evaluation results useful. At the end, the consultant prepares an inception report. The commissioning agency should review the inception report carefully before substantial data collection begins.

5Manage the process without compromising independence

The commissioning agency should provide:

  • Relevant project documentation
  • Access to stakeholders
  • Administrative support
  • Clarification of factual information
  • Timely feedback on deliverables

However, the agency should not attempt to influence findings or conclusions.

A useful distinction is:

Management responsibility: ensuring a sound evaluation process.

Evaluator responsibility: making independent professional judgements based on evidence. The evaluator should be free to report findings that may be critical of the intervention.

6Monitor quality during data collection and analysis

Do not wait until the final report to identify problems.

Periodic check-ins can assess:

  • Whether data collection is proceeding as planned
  • Whether important stakeholders have been reached
  • Whether the evidence is sufficient to answer the evaluation questions
  • Whether methodological changes are necessary
  • Whether emerging findings require additional investigation

Changes to the evaluation design should be documented and justified.

7Review of the draft report

The draft report should undergo a systematic quality review.

Reviewers should examine:

  • Whether all evaluation questions have been addressed
  • Whether findings are supported by adequate evidence
  • Whether multiple sources have been considered
  • Whether conclusions logically follow from findings
  • Whether recommendations address identified issues
  • Whether limitations are transparently reported
  • Whether the report is clear and useful for intended users

Avoid turning the review into an exercise in rewriting the evaluator's conclusions simply because they are inconvenient or unexpected.

TemplateQuality checklist for reviewing evaluation reportDownload coming soon

8Finalize and communicate the evaluation

Before accepting the final report:

  • Confirm that factual inaccuracies have been corrected.
  • Confirm that methodological issues have been addressed.
  • Confirm that the evaluator has explained important limitations.
  • Ensure that conclusions and recommendations are clearly presented.
  • Document significant comments that were not accepted, where appropriate.

Then communicate the results to intended users in an accessible form.

Possible products include:

  • Executive summary
  • Presentation
  • Management response
  • Briefing note
  • Infographic
  • Learning session

9Follow up on evaluation use

Evaluation management does not end when the final report is delivered.

The commissioning agency should establish:

  • Who will consider the findings
  • What decisions are expected
  • Which recommendations require action
  • Who is responsible for follow-up
  • What timeframe applies
  • How implementation will be monitored

The development of a management response and follow-up action plan serves to ensure that the recommendations are addressed and acted upon.

TemplateSample evaluation management response and action plan templateDownload coming soon

Key message

Managing an external evaluation is not about controlling the evaluator. It is about creating the conditions for an evaluation that is credible, independent, relevant and useful.

Was this guide useful?

Your feedback helps us improve the M&E Toolbox. It takes less than a minute.

How useful was this guide, from 1 (low) to 5 (high)?

Optional

0 / 2000

Your feedback is anonymous. We do not ask for your name or email address.

Back to the M&E Toolbox