How to conduct risk analysis in results-based management?

Results are only as credible as the assumptions beneath them. Risk analysis names what could stop outputs from becoming outcomes, and what the team will do about it.

What this helps you do

Identify, rate and respond to risks along your results chain, and record them so they can be reviewed during implementation.

When to use it

At design, during periodic reviews, and whenever the context of the intervention changes.

1Key concepts before you start

TermWhat it means in practiceExample
AssumptionA condition outside your control that must hold for one level of the results chain to lead to the next.The ministry retains trained staff after the training.
RiskAn uncertain event that would harm results if it occurs; often an assumption that fails.High turnover removes 40% of trained staff within a year.
Likelihood and impactHow probable the risk is over the intervention period, and how severely results would suffer.Each rated 1 (low) to 3 (high).
MitigationAction that reduces likelihood or impact.Train a pool of trainers; agree a retention clause.
Risk ownerThe named person who monitors the risk and triggers the response.Intervention manager, implementing agency.

Rule of thumb

Every risk should be traceable to a specific link in the results chain (activities, outputs, outcomes, impact).

2Start from the results framework

Review the intervention’s results framework and, where available, its theory of change. Look at the main links between activities, outputs and outcomes and ask: what important conditions need to be met for this to happen, and what could disrupt it?

Do this

  • Have the results framework and theory of change at hand
  • Identify the key assumptions for the more important links in the results chain
  • Focus particularly on conditions that are not fully within the intervention’s control

Common mistake

Leaving assumptions blank in the logframe, or confusing them with risks. Write the assumption as a positive condition; the matching risk is its failure.

3Identify risks with stakeholders

Discuss risks with the project team and, where feasible, government counterparts, implementing partners and other stakeholders who can provide useful perspectives. Consider political, economic, social, technological, legal and environmental (PESTLE) factors, as well as institutional capacity, resources and implementation arrangements.

Do this

  • Draw on the knowledge of the project team and relevant partners
  • Consider external factors as well as institutional and implementation constraints
  • Prioritize a manageable number of risks that could materially affect results

Common mistake

Listing 50 risks. Focus on risks that are sufficiently important and plausible to influence project decisions.

4Describe each risk clearly

Describe risks specifically enough to understand what may happen, why it matters, and which result could be affected.

Example: Because of the upcoming elections (cause), line ministries may freeze new initiatives (event), delaying adoption of the policy at Outcome 2 (effect).

Do this

  • Describe the risk in concrete terms
  • Identify important causes or drivers where known
  • Link the risk to the result(s) it could affect

Common mistake

Generic labels such as “political instability” or “funding” without explaining how they could affect the intervention.

5Rate likelihood and impact

Score each risk from 1 to 3 for likelihood and for impact, then multiply. Scores of 6–9 are high and need active mitigation and senior management attention; 3–4 are medium and need a plan and regular watch; 1–2 are low and are monitored only.

Try it: rate a risk

Likelihood
Impact
6HighNeeds active mitigation and senior management attention

Do this

  • Give every risk a likelihood and an impact score
  • Flag high risks for senior management attention

Common mistake

Giving most risks the same rating. The purpose of the exercise is to distinguish their relative importance, not simply to complete the matrix.

6Decide the response and assign an owner

For high risks, identify a practical response. Depending on the nature of the risk, this may involve reducing its likelihood or impact, adjusting implementation arrangements, accepting and monitoring it, or reconsidering an activity. Identify who is responsible for monitoring the risk and, where useful, what change or warning sign should prompt action.

Do this

  • Choose a response for every high and medium risk
  • Identify who will monitor each significant risk
  • For important risks, identify useful warning signs or conditions for action

Common mistake

Listing mitigation measures that are not realistic within the project’s resources or implementation arrangements.

7Record and periodically review the risks

Record the significant risks, their ratings and agreed responses in the project documentation or risk register. Revisit them during implementation, particularly when circumstances change at periodic project reviews. Where relevant, reflect risk responses in the workplan, monitoring sheet and budget.

Do this

  • Keep a record of the significant risks and agreed responses
  • Reflect mitigation measures in implementation plans where relevant
  • Review risks as part of periodic project monitoring and when important changes occur

Common mistake

Treating the risk assessment as something completed for project approval and not revisited when the operating context changes.

TemplateRisk register templateDownload coming soon

Key message

Risk analysis is not just a form completed during project design. It helps make the results framework more realistic by identifying important uncertainties, considering how they can be managed, and revisiting them as circumstances change.

Was this guide useful?

Your feedback helps us improve the M&E Toolbox. It takes less than a minute.

How useful was this guide, from 1 (low) to 5 (high)?

Optional

0 / 2000

Your feedback is anonymous. We do not ask for your name or email address.

Next in the cycle

How to manage an evaluation conducted by an external consultant?

Make the project’s risk analysis available to the evaluator as part of the relevant project documentation.