1Results hierarchy
The results hierarchy explains how the project’s work is expected to contribute to change.
| Level | Description | Examples |
|---|---|---|
| Objective or impact | Longer-term development changes to which the project contributes | Reduced food waste and improved livelihoods Improved environmental sustainability and resilience of communities to climate change |
| Outcomes | Specific changes in the behaviour, practices and of the target group that occur as a result of achieving outputs. | Farmers regularly use solar dryers effectively Governments develop or formally adopt new policies. |
| Outputs | Tangible and immediate deliverables of a project that result directly from activities. | Farmers can operate solar dryers correctly Enhanced institutional capacities to formulate and implement climate adaptation policies. |
Activities are the actions undertaken to produce outputs, such as conducting training or preparing a study. They are included in the logframe to explain how results will be achieved but are not results themselves.
Activities produce outputs; outputs contribute to outcomes; and outcomes contribute to the objective. Each connection needs a plausible explanation. Delivering training, for example, may strengthen participants’ skills, but applying those skills may also require institutional support, authority or resources.
Project teams generally have more direct control over activities and outputs than over outcomes and broader objectives. The framework should reflect what the project can realistically deliver and influence.
Key principle
Completing activities does not, by itself, demonstrate that the intended outcomes have been achieved.
2Indicators, baselines and targets
Indicators are quantitative or qualitative measures used to assess progress towards results. They specify the observable change that will be tracked, rather than simply restating the result.
A baseline describes the starting position. A target specifies the intended level of achievement by a defined time. Together, these make it possible to assess progress.
For example:
- Indicator: Number of participating authorities that formally endorse a school zone improvement plan based on safety assessments.
- Baseline: No participating authorities have endorsed such a plan at project start, subject to verification.
- Target: Three participating authorities by month 18.
Useful indicators are specific, measurable, achievable, relevant and time bound. One result may require more than one indicator. Measures should reflect the result being assessed: workshop attendance measures participation, while evidence of changed practice is needed to assess application of learning.
Watch out
Do not assume that the baseline is zero. The starting position needs to be established using available evidence.
For more guidance on formulating indicators, please refer to the tool guide on indicators.
3Means of verification
Means of verification identify the sources and methods used to determine whether an indicator has been achieved. Depending on the indicator, these may include official records, approved plans, surveys, assessments or interviews.
The evidence should be relevant, credible and feasible to obtain. Its availability, collection costs and timing should be considered when indicators are selected. Monitoring arrangements should also clarify who will collect and retain the evidence.
For the indicator above, endorsed plans and official decision records would provide evidence of formal endorsement. Participants’ statements that they intend to prepare plans would not establish the same result.
Key principle
An indicator is useful only if credible evidence can be obtained to track it.
4Risks and assumptions
Assumptions are conditions expected to hold for the results chain to work. Risks are potential events or conditions that could undermine it.
For example, trained officials may need to remain in relevant positions and have opportunities to apply their skills. Staff turnover, limited budgets or changes in institutional priorities could interrupt that pathway.
Making these dependencies explicit helps explain why outputs may or may not lead to outcomes. It also supports decisions on mitigation measures and issues requiring attention during implementation.
Watch out
A logframe describes an expected pathway to change; it does not guarantee that the change will occur.
5Using the framework throughout the project
During design, the logframe helps test the project’s scope and internal logic. During implementation, it provides a reference for monitoring and reporting. During evaluation, it supports assessment of the intended results and factors affecting achievement.
The framework should be reviewed as evidence and circumstances change. Justified revisions should be documented and approved under applicable procedures, with the original baseline retained for comparison.
Agency and funding templates vary. In the ESCAP format described in the accompanying training, activity rows do not require result indicators or means of verification. Other templates may structure these requirements differently.
6An example in practice
The following illustrative results chain concerns a project supporting local authorities to improve school zone safety.
| Level | Example |
|---|---|
| Objective | Reduced road crash injuries and fatalities in selected school zones. |
| Outcome | Local authorities use school zone safety assessments to prioritize improvements. |
| Output | Local technical teams can assess school zone safety and prepare prioritized improvement proposals. |
| Activities | Conduct joint assessments, provide training and coach teams on proposal preparation. |
The project supports technical capacity and planning. Authorities remain responsible for approving plans and financing physical improvements. Endorsement of a plan can demonstrate a planning decision, but it does not establish that construction has been completed or injuries have fallen. Those changes require separate evidence.